Signing contract for repair of district roads (Gościeradów/Szastarka)
On 20 October 2023, a contract was signed for the implementation of the following project: “Repair of district roads No. 2717L from km 0+808 to km 1+369, No. 2712L from km 0+000 to km 1+111 and from km 5+060 to km 5+291, and No. 2743L from km 0+400 to km 0+845 and from km 1+289 to km 1+846”.
WOD-BUD Sp. z o.o. shall implement the following stages of the investment:
Stage 2 Repair of district road No. 2712L from km 0+000 to km 1+111 and from km 5+060 to km 5+291 in the Gościeradów Commune – PLN 1,365,141.03
Stage 3 Repair of district road No. 2743L from km 0+400 to km 0+845 and from km 1+289 to km 1+846 in the Szastarka Commune – PLN 1,429,366.06
The following works shall be performed under the contract:
- preparatory work,
- earthwork,
- underpasses,
- road structure drainage,
- base and sub-base layers,
- surfaces,
- repaving of existing driveways,
- road elements,
- markings,
- finishing work.
The contract for the aforementioned works was signed by Paweł Kudrel, Governor of the Kraśnik District, Andrzej Misztal, Deputy Governor of the Kraśnik District, Iwona Szymańska, Treasurer of the Kraśnik District, and Jędrzej Wojtaszek, Commercial Representative of the Management Board of WOD-BUD Sp. z o.o.
The project is financed with the resources from the Government Road Development Fund at the request of the Kraśnik District ‒ the District Road Authority in Kraśnik.